Rio Grande Emerges as Brazil’s Best-Prepared Port for Offshore Wind

According to the study, Brazil has one of the world’s largest offshore wind energy potentials, and the enactment of the Offshore Wind Energy Act (Law No. 15,097/2025) is expected to accelerate the investment needed to support the country’s energy transition.

Commissioned by the Danish Energy Agency (DEA) from consulting firm COWI, as part of a bilateral partnership with Brazil’s Ministry of Ports and Airports (MPOR) and Ministry of Mines and Energy (MME), the study “Current Capacities and Prospects of Brazilian Ports for Offshore Wind Energy Projects” assessed the Brazilian coastline to identify potential bases for the country’s future offshore wind industry. Six ports, two in each region, were inspected in March 2026 and evaluated under three scenarios: large offshore wind farms (Large Offshore), nearshore wind farms (nearshore), and operations and maintenance (O&M).

According to the study, Brazil has one of the world’s largest offshore wind energy potentials, and the enactment of the Offshore Wind Energy Act (Law No. 15,097/2025) is expected to accelerate the investment needed to support the country’s energy transition. At present, however, none of the ports inspected can accommodate a large-scale offshore wind terminal, primarily due to insufficient yard space, inadequate quay load capacity and the absence of dedicated areas for offshore wind operations.

In the Northeast, Pecém, where the required upgrades are estimated at US$356.5 million over 6.5 years, and Suape, at US$187.5 million over 5.5 years, would require major infrastructure works. In the Southeast, the ports of Açu, with estimated investment of US$129 million over 4.5 years, and Central, at US$142.5 million over 5.5 years, would need to develop terminals that do not yet exist.

Southern Brazil, by contrast, offers the best-prepared and most cost-effective alternative. The study indicates that the Port of Rio Grande is ideally located to serve offshore wind projects in the region and that the Estaleiros do Brasil Ltda. (EBR) shipyard would require the lowest investment across all scenarios assessed: US$64 million over three years for Large Offshore, US$27.5 million over 2.5 years for nearshore, and US$5 million over two years for an O&M base.

Located less than 200 kilometres from the areas proposed for offshore wind farms, EBR has a 530-metre quay with a depth of 12 metres, designed for heavy industrial operations, as well as approximately 165 hectares of landside area, with cranes and warehouses. Situated on the São José do Norte side of the channel, the shipyard does not compete for space with the Superporto do Rio Grande and allows manufacturing, assembly and load-out activities to be concentrated at a single site.

Certain points in the study warrant clarification and, in this author’s view, further strengthen EBR’s attractiveness. The Port of Rio Grande is currently managed by the state-owned company Portos RS, successor to the Superintendência do Porto do Rio Grande (SUPRG), which is referred to by COWI. This structure provides greater administrative and financial autonomy and enables more agile decision-making. The Rio Grande entrance channel is also not materially affected by tides, allowing access to remain open 24 hours a day, subject only to weather conditions.

The most important aspect, however, is the regulatory framework. The study notes that authorisations for the use of port areas may cause delays to project schedules, but does not specifically examine EBR’s circumstances. At the shipyard, only the quay lies within the boundaries of the organised port and is operated under a fee-based right-of-use agreement with Portos RS, in an area already designated as non-operational and allocated to shipbuilding and offshore activities. EBR’s entire landside area is privately owned and lies outside the organised port boundaries, allowing manufacturing, assembly and storage activities to be carried out without requiring a lease, public tender or agreement with MPOR, Portos RS or the Agência Nacional de Transportes Aquaviários (Antaq).

Also in Southern Brazil, the Port of Imbituba, managed by SCPar, emerges as a complementary option. Although the study considers a Large Offshore terminal unfeasible within the port’s current boundaries due to space constraints and insufficient quay capacity, it identifies an important role for Imbituba in nearshore and O&M activities, with estimated investment of approximately US$35.5 million under a shared-use model or US$154 million for the construction of a new quay dedicated to offshore wind operations.

Existing infrastructure, lower costs, shorter implementation times and legal certainty make the Port of Rio Grande, and EBR Shipyard in particular, the best-prepared location in Brazil to serve as an industrial and logistics base for offshore wind, from the installation of the first wind farms through to their operation. These competitive advantages are already attracting interest from major industry players and are expected to establish Rio Grande as a leading hub for Brazil’s future offshore wind industry.

Caption: A study commissioned by the Danish Energy Agency estimates that adapting EBR Shipyard to support large offshore wind farms would require an investment of US$64 million, with an estimated implementation period of three years.